Case Study: A14T Crankshaft Automatic Production Line, Guilin
● Production Schedule: 300 working days/year, 3 shifts (24h/day), equipment uptime 80%
● Cycle Time (Finished Part): ≤ 120 s/pc
● Average Machining Cycle (4-cylinder, excluding robot handling): < 110 s
● Robot Loading/Unloading Cycle: ≤ 10 s (excluding machine door opening/closing)
● Model Changeover Time: ~8 hours (manual adjustment)
● Product Types: 3-cylinder and 4-cylinder crankshafts (same loading cycle)
The production line is designed for high-efficiency crankshaft machining, with synchronized robot handling and CNC machining processes. Truss robots enable fast and stable material transfer between stations, supporting continuous automated production of multi-cylinder crankshaft variants.